Here’s what we know about the waterline replacement project and how soon it will be complete, per the City of Dayton Construction Inspector overseeing SP waterline project:
- The work has been delayed due to supply chain issues (the shipment of new fire hydrants).
- After Johnson is complete (Morton to Wayne), work will begin sequentially on Bonner (Hickory to Oak), then James (Hickory to Johnson) and finally Bradford (James to Theobald).
- The entire project is scheduled to be completed by October 1, 2022.
- The City will alert neighbors as the work progresses.
We’ll do our best to post updates here.
Related posts
Toddler Playground Fundraiser in Full Swing!
If you love to see young families sharing in happy, healthy outdoor play, please donate!
Looking Back: HSPI had a busy 2023
In case you missed it: HSPI had a very challenging 2023. Thanks to many hard-working volunteers, we accomplished a great deal. We’re taking a moment to review before we face whatever 2024 will bring.
Wayne Avenue Traffic Safety Coalition: Community Update
WATSC recently held a media event at Ghostlight Coffee. It was attended by business and education leaders, City of Dayton commissioners and staff, Dayton traffic engineers, and concerned neighbors. We commemorated the loss of Jennifer Johnson, struck and killed by speeding driver at Wayne and Clover.