Here’s what we know about the waterline replacement project and how soon it will be complete, per the City of Dayton Construction Inspector overseeing SP waterline project:
  • The work has been delayed due to supply chain issues (the shipment of new fire hydrants).
  • After Johnson is complete (Morton to Wayne), work will begin sequentially on Bonner (Hickory to Oak), then James (Hickory to Johnson) and finally Bradford (James to Theobald).
  • The entire project is scheduled to be completed by October 1, 2022.
  • The City will alert neighbors as the work progresses.
We’ll do our best to post updates here.